Construction is underway to turn the unused space upstairs behind the sanctuary into a balcony that will provide fifty extra seats for our growing congregation.
UPDATE 2-13-26



UPDATE 2-12-26

UPDATE 2-10-26


UPDATE 2-5-26



UPDATE 1-29-26


UPDATE 1-23-26

UPDATE 1-22-26
Progress has been made on the new Balcony. The scaffolding is in place, so please be aware of some changes for the duration of the construction. The west aisle entry into the sanctuary is blocked and cannot be used past the sound booth, because the scaffolding over the sound booth is too wide. Please use the center and east aisles to enter the sanctuary. Also, the back two pews on the east side have been removed to accommodate the scaffolding. Foam insulation has been sprayed upstairs. The sound panels are off the wall in the sanctuary. The block walls in front of the balcony have been removed, but they are planning to leave the drywall up for dust control.